Project Start Date: Fri 8/1/08
Project Finish Date: Thu 9/30/10
| 1 | 1 | Initial Design and Planning | |||
| 2 | 1.1 | Design | |||
| 3 | 1.1.1 | Technical Evaluation of Existing PDG Computing System | |||
| 4 | 1.1.2 | Initial Design | 3 | ||
| 5 | 1.1.3 | Detailed Design | 4,15 | ||
| 6 | 1.2 | Architecture | 4 | ||
| 7 | 1.2.1 | Draft Architecture | |||
| 8 | 1.2.2 | Install Test Version of JBOSS | 7 | ||
| 9 | 1.2.3 | Evaluate Architecture | 8 | ||
| 10 | 1.2.4 | Evaluate Software Components | 9 | ||
| 11 | 1.2.5 | Finalize System Architecture | 10,15 | ||
| 12 | 1.3 | Project Plan | 4 | ||
| 13 | 1.3.1 | Prepare Project Plan | |||
| 14 | 1.3.2 | Attend PDG Review | |||
| 15 | 1.3.3 | Revise Project Plan | 14 | ||
| 16 | 1.4 | Configuration Management | 4 | ||
| 17 | 1.4.1 | Set Up Build Environment | 7 | ||
| 18 | 1.4.2 | Set Up Configuration Management | 17,15 | ||
| 19 | 2 | Database Abstraction Layer | 11 | ||
| 20 | 2.1 | Design Database Schema | |||
| 21 | 2.2 | Implement Schema Changes | 20 | ||
| 22 | 2.3 | Investigate Alternative Display Technologies | 21 | ||
| 23 | 2.4 | Design Database Abstraction Layer | 22 | ||
| 24 | 2.5 | Implement Database Abstraction Layer | 23 | ||
| 25 | 2.6 | Integration Test | 24 | ||
| 26 | 2.7 | Production Test | 25 | ||
| 27 | 2.8 | Documentation | 26 | ||
| 28 | 3 | Data Analysis Environment | 19 | ||
| 29 | 3.1 | Design Data Analysis Environment | |||
| 30 | 3.2 | Implement Data Analysis Environment | 29 | ||
| 31 | 3.3 | Integration Test | 30 | ||
| 32 | 3.4 | Production Test | 31 | ||
| 33 | 3.5 | Documentation | 32 | ||
| 34 | 4 | Encoder Interface and Literature Search Interface | 131 | ||
| 35 | 4.1 | Encoder Interface | |||
| 36 | 4.1.1 | Design | |||
| 37 | 4.1.1.1 | Server Design | |||
| 38 | 4.1.1.2 | User Profile Management Database Schema Changes Design | |||
| 39 | 4.1.1.3 | User Interface Design | 38 | ||
| 40 | 4.1.2 | Development | 36 | ||
| 41 | 4.1.2.1 | Server Development | |||
| 42 | 4.1.2.2 | User Profile Management Database Schema Development | |||
| 43 | 4.1.2.3 | User Interface Development | 42 | ||
| 44 | 4.1.3 | Unit Tests | 40 | ||
| 45 | 4.1.4 | Integration Test | 44 | ||
| 46 | 4.1.5 | Production Test | 45 | ||
| 47 | 4.1.6 | Documentation | 46 | ||
| 48 | 4.2 | Literature Search Interface | 35 | ||
| 49 | 4.2.1 | Design | |||
| 50 | 4.2.1.1 | Server Design | |||
| 51 | 4.2.1.2 | User Interface Design | 50 | ||
| 52 | 4.2.2 | Development | 49 | ||
| 53 | 4.2.2.1 | Server Development | |||
| 54 | 4.2.2.2 | User Interface Development | 53 | ||
| 55 | 4.2.3 | Unit Tests | 52 | ||
| 56 | 4.2.4 | Integration Test | 55 | ||
| 57 | 4.2.5 | Production Test | 56 | ||
| 58 | 4.2.6 | Documentation | 57 | ||
| 59 | 5 | Database Viewer | |||
| 60 | 5.1 | Design | |||
| 61 | 5.1.1 | Server Design | 53 | ||
| 62 | 5.1.2 | User Interface Design | 61,34 | ||
| 63 | 5.2 | Development | |||
| 64 | 5.2.1 | Server Development | 61 | ||
| 65 | 5.2.2 | User Interface Development | 62 | ||
| 66 | 5.3 | Unit Tests | 63 | ||
| 67 | 5.4 | Integration Test | 66 | ||
| 68 | 5.5 | Production Test | 67 | ||
| 69 | 5.6 | Documentation | 68 | ||
| 70 | 6 | Review Author Interface | 59 | ||
| 71 | 6.1 | Design | |||
| 72 | 6.2 | Development | 71 | ||
| 73 | 6.3 | Unit Test | 72 | ||
| 74 | 6.4 | Integration Test | 73 | ||
| 75 | 6.5 | Production Test | 74 | ||
| 76 | 6.6 | Documentation | 75 | ||
| 77 | 7 | Refactor Existing Auxiliary Programs | 131 | ||
| 78 | 7.1 | Design | |||
| 79 | 7.2 | Development | 78 | ||
| 80 | 7.3 | Unit Tests | 79 | ||
| 81 | 7.4 | Integration Test | 80 | ||
| 82 | 7.5 | Production Test | 81 | ||
| 83 | 7.6 | Documentation | 82 | ||
| 84 | 8 | User Profile Management/Mailing System | 70,59 | ||
| 85 | 8.1 | Design | |||
| 86 | 8.2 | Development | 85 | ||
| 87 | 8.3 | Unit Tests | 86 | ||
| 88 | 8.4 | Integration Test | 87 | ||
| 89 | 8.5 | Production Test | 88 | ||
| 90 | 8.6 | Documentation | 89 | ||
| 91 | 9 | Status Reporting | 84,59 | ||
| 92 | 9.1 | Design | |||
| 93 | 9.2 | Development | 92 | ||
| 94 | 9.3 | Unit Test | 93 | ||
| 95 | 9.4 | Integration Test | 94 | ||
| 96 | 9.5 | Production Test | 95 | ||
| 97 | 9.6 | Documentation | 96 | ||
| 98 | 10 | System Monitoring | 91,34 | ||
| 99 | 10.1 | Design | |||
| 100 | 10.2 | Development | 99 | ||
| 101 | 10.3 | Unit Test | 100 | ||
| 102 | 10.4 | Integration Test | 101 | ||
| 103 | 10.5 | Production Test | 102 | ||
| 104 | 10.6 | Documentation | 103 | ||
| 105 | 11 | Verifier Interface | 91 | ||
| 106 | 11.1 | Design | |||
| 107 | 11.2 | Development | 106 | ||
| 108 | 11.3 | Unit Test | 107 | ||
| 109 | 11.4 | Integration Test | 108 | ||
| 110 | 11.5 | Production Test | 109 | ||
| 111 | 11.6 | Documentation | 110 | ||
| 112 | 12 | Institution Database Interface | 84 | ||
| 113 | 12.1 | Design | |||
| 114 | 12.2 | Development | 113 | ||
| 115 | 12.3 | Unit Test | 114 | ||
| 116 | 12.4 | Integration Test | 115 | ||
| 117 | 12.5 | Production Test | 116 | ||
| 118 | 12.6 | Documentation | 117 | ||
| 119 | 13 | Editor Interface | 112,105 | ||
| 120 | 13.1 | Design | |||
| 121 | 13.2 | Development | 120 | ||
| 122 | 13.3 | Unit Test | 121 | ||
| 123 | 13.4 | Integration Test | 122 | ||
| 124 | 13.5 | Production Test | 123 | ||
| 125 | 13.6 | Documentation | 124 | ||
| 126 | 14 | Final System Integration and Test | 119,59,105 | ||
| 127 | 14.1 | Integration Test | |||
| 128 | 14.2 | Production Test | 127 | ||
| 129 | 14.3 | Documentation | 128 | ||
| 130 | 14.4 | Training and Transition Plan | 129 | ||
| 131 | 15 | Start of Fiscal Year 2009 |